Project time
05.2019 - 10.2020
Location:
STOCKHOLM, SWEDEN

ABOUT THE PROJECT

Between 2016 and 2021, construction works of new buildings were carried out at the hospital. The project includes two new care buildings adapted for maternity care as well as emergency and intensive care. The project also includes a new, larger emergency room and emergency room, as well as renovations to existing buildings that include new operating theaters and a new, larger X-ray department. /www.locum.se/

The ART8 team supplied and installed flooring materials for a total area of ​​more than 19,000 m2. We used Bostik 6000 primer, Bostik Combi 10 floor putty to prepare the base floor. We used Bostik Startac glue for gluing.

GENERAL CONTRACTORS

  • Skanska Sverige AB

ARCHITECTS

  • Arkitema Architects AB

MATERIALS

  • PVC free vinyl Upofloor Zero – 17500.0 m2
  • PVC free vinyl Upofloor Zero – 15250.0 tm
  • PVC free vinyl Wineo 1500 – 900.0 m2
  • PVC vinyl Forbo Surestep – 1500.0 m2
  • PVC vinyl Forbo Surestep – 1950.0 m2

ADDITIONALLY

  • According to the customer’s wishes, we covered the entire area with protective paper and pressboard to protect the flooring during the entire construction period. According to the client’s instructions and our recommendations, we performed the end filling of the floor to achieve an excellent final result. – 19900.0 m2
  • Delivered MDF baseboards with Wineo finish – 700.0 tm
  • Duuri PL31 skirting boards delivered – 700.0 tm